Construction Update March 2010
Earthworks continued at the plant site with workers starting on piling, footings and steel structure work. About 2km of pipeline has been laid and 14km of the easement prepared for pipelaying.
Traffic advisories
- 24 March 2010 Temporary Closure McCormacks Road
- 12 March 2010 Temporary closure of Cardinia Road, Cardinia
Other activities
- Community Liaison Group meeting held 25 March 2010
- Jobs advertised (current)
- AquaSure community updates - 1 March 2010 and 22 March 2010