Project Timeline

The project was announced in 2007, with an Environment Effects Statement prepared in 2008 in parallel with a tendering process to award the contract, which was signed in July 2009. Construction began in September 2009 and commissioning is currently expected in February 2013.

The timeline for the project is as follows:

28 February 2012
Current scheduled date for Reliability Testing Finalisation, i.e., plant passes all reliability testing
15 November 2012
Current scheduled date for Commercial Acceptance, i.e., plant first produced water at 150GL pa rate
1 April 2012 First annual water order placed
7 March 2012
Power cable live
24 February 2012
Flooding of marine tunnels completed
January 2012
Fibre optic cable installation completed
November 2011
Hydrotesting of transfer pipeline completed
24 October 2011
Transfer pipeline installation completed
September 2011
Power cable installation completed
16 March 2011
Outlet tunnel completed
3 February 2011
Jack up barge departs
1 December 2010
Intake tunnel completed
22 October 2010
Project named Project Finance Deal of the Year at the CFO Awards
11 October 2010
Jack up barge arrives on site at Wonthaggi
27 September 2010
Jack up barge arrives at Western Port
16 September 2010
Job opportunities grow from desalination green roof
6 September 2010
Start of Tunnel Boring Machine 2 for Outlet Tunnel
27 July 2010 Start of Tunnel Boring Machine 1 for Inlet Tunnel
June 2010
Project named on Infrastructure Journal's Infrastructure 100 list
May 2010 Power infrastructure installation begins
26 April 2010
Project named Desalination Deal of the Year at Global Water Awards
31 March 2010
Project named Infrastructure and Project Finance Deal of the Year (Asia) by The Banker (Financial Times)
11 March 2010
Project named Global Deal of the Year and Deal of the Year - PPP (2009) at the Infrastructure Journal Infrastructure Awards
11 March 2010
Project wins Infrastructure Partnerships Australia Financial Excellence Award
10 February 2010
Project awarded Australian & NZ Deal of the Year (2009) by International Financing Review Australia
8 February 2010
Project named Best Finance Project Finance Deal in Australia (2009) by Asiamoney magazine
6 February 2010
New Community Information Centre opens in Wonthaggi
4 February 2010
Project wins Asia Pacific Project Financing of the Year and Best Australasia Deal of the Year at Euroweek Asia Pacific Loan Awards
4 February 2010
First pipe laid at Clyde North
20 January 2010
Project awarded PPP Deal of the Year Asia Pacific (2009) by Project Finance International
January 2009
Offers of compensation sent to landowners on the Cranbourne easement
December 2009
Offers of compensation sent to landowners on the pipeline and power easement
26 November 2009
Project Summary tabled in Parliament. Project contract released
19 November 2009
Syndication of debt completed. Government guarantee no longer required.
30 October 2009
Independently Chaired Community Liaison Group meetings commence
30 September 2009 Construction starts
2 September 2009 Financial close
30 July 2009
Contract awarded to AquaSure
28 May 2009
Government announces underground power option preferred
27 March 2009 Request for Proposal closes - bid assessment begins
19 March 2009
Federal Minister for Environment, Water, Heritage and the Arts approves project under EPBC Act
3 March 2009
EPA Works Approval Application approved
9 January 2009
EES Assessment by Planning Minister announced
4 December 2008
EES Inquiry Panel submits report to Planning Minister
October/November  2008
EES Inquiry Panel Hearing
30 September 2008
Requests for Proposals for construction and operation issued to two shortlisted bidders
30 September 2008 EES and WAA public exhibition closed
20 August 2008 EES report and EPA Works Approval Application (WAA) submitted and exhibited for public comment
August 2008
Formal Council Liaison Group meetings commence
24 July 2008
Expressions of Interest closed
4 June 2008
Invitation for Expressions of Interest to bid for project issued
4 May 2008
EES Scoping Requirements released
19 March 2008 Public comment on Draft EES Scoping Requirements
7 February 2008 Commonwealth Government accredits EES process assessment under Environment Protection and Biodiversity Conservation Act 1999 (EPBC)
28 December 2007
Planning Minister announced EES to be undertaken
30 November 2007
EES Referral submitted by DSE
19 September 2007 Government announces desalination project will be delivered as a PPP and Project Information Office opens in Wonthaggi
19 June 2007
The Next Stage of the Government's Water Plan announced
June 2007
Feasibility Study completed